Examples / Operator assessment
Does the expansion still fit
when demand changes?
Method: grid only (Headroom v2.1.0)
Synthetic example. Not a customer result.
Not supported. Higher existing-demand bounds leave a −190 kW margin after the protected grid commitment during October 26, 2026, 12:00–13:00 UTC.
Why it matters: the original proposal had electrical support. The changed records no longer support that same expansion profile over the full six-hour period. A connection rating alone does not settle the decision.
Next action: obtain the basis for the higher demand bounds and have the responsible engineer confirm the protected commitment and applicable limits before relying on the expansion assumption.
Example site: Holding A. Assessed period: October 26, 2026, 09:00–15:00 UTC. One import-only grid service and one internal electrical section; no embedded generation or storage. Thermal and combined findings: Not evaluated.
The proposal stays the same. The demand evidence changes.
Method: grid only (Headroom v2.1.0)
Synthetic example. Not a customer result.
The original electrical assessment is Supported under the stated synthetic assumptions, with a minimum margin of +580 kW. The reassessment is Not supported. Only three existing-demand bounds change; the added-load profile, ratings and protected commitments stay the same.
Grid service: 6,000 kW, with 400 kW protected. Internal section: 6,700 kW, with 150 kW protected. These are separate boundaries and commitments, not amounts to subtract twice from one limit.
| Hour | Original demand | Changed demand | Added load | Original margin | Reassessed margin |
|---|---|---|---|---|---|
| 09:00–10:00 | 3,100 | 3,100 | 900 | +1,600 | +1,600 |
| 10:00–11:00 | 3,450 | 3,450 | 900 | +1,250 | +1,250 |
| 11:00–12:00 | 3,800 | 4,380 | 1,000 | +800 | +220 |
| 12:00–13:00 | 4,020 | 4,790 | 1,000 | +580 | −190 |
| 13:00–14:00 | 3,700 | 4,560 | 1,000 | +900 | +40 |
| 14:00–15:00 | 3,250 | 3,250 | 900 | +1,450 | +1,450 |
Margins are after the grid commitment. At 12:00–13:00, 6,000 − 400 − 4,790 − 1,000 = −190 kW. The physical grid rating is not exceeded, but the remaining allowance after protection is. One failed interval prevents support for the full supplied period; this does not establish safe shorter service.
Input basis and the records to confirm
These six one-hour values are assumed upper bounds applying throughout each interval, not energy-derived averages or instantaneous peak measurements. Existing demand includes baseline auxiliaries. Added load includes information technology (IT), 130 kW of cooling electricity and 50 kW of other auxiliaries. Additional IT is 720, 720, 820, 820, 820 and 720 kW by hour.
The operator supplies the source and higher-resolution basis for each bound and the changed operating context. The responsible engineer confirms the mapping, applicable ratings and complete, non-overlapping commitments. Differences between records do not establish their cause. The failure is located at the supplied interval start, not an inferred crossing between measurements.
A separately assessed alternative has positive electrical margin.
Method: grid only (Headroom v2.1.0)
Synthetic example. Not a customer result.
Supported under the stated synthetic assumptions, with a minimum +160 kW margin during 12:00–13:00 UTC.
Why it matters: it identifies a specific proposal worth reviewing, not a proven operating remedy or evidence that an operator accepts a lower load. It does not establish thermal support.
Next action: have the operator and responsible engineer review the alternative's operational acceptability and assumptions. Assess any required cooling decision separately.
Decision: would a different proposed load profile fit the changed demand records? The separately evaluated alternative uses total added loads of 750, 750, 800, 650, 800 and 750 kW across the same six hours. Only the IT portion changes. The 130 kW of added cooling electricity and 50 kW of other auxiliaries included in those totals stay fixed, as do the changed existing-demand records.
Alternative margins by hour
| Hour UTC | Added load | Grid margin after protection |
|---|---|---|
| 09:00–10:00 | 750 | +1,750 |
| 10:00–11:00 | 750 | +1,400 |
| 11:00–12:00 | 800 | +420 |
| 12:00–13:00 | 650 | +160 |
| 13:00–14:00 | 800 | +240 |
| 14:00–15:00 | 750 | +1,600 |
At 12:00–13:00, 6,000 − 400 − 4,790 − 650 = +160 kW. Thermal and combined findings: Not evaluated.
Three holdings. Three different next decisions.
Method: grid only (Headroom v2.1.0)
Synthetic example. Not a customer result.
For an owner, operator or investor reviewing several holdings: which holding supports the same added electrical profile, and which constraint or missing record needs attention next?
This common comparison uses 900, 900, 1,000, 1,000, 1,000 and 900 kW over October 26, 2026, 09:00–15:00 UTC. Each holding has one import-only service and one internal section, with different existing demand, limits and commitments. Results depend on the stated synthetic assumptions.
| Holding | Electrical finding | Limiting condition | Next action |
|---|---|---|---|
| A / original records | Supported | Grid service after protection: +580 kW at 12:00–13:00 UTC. | Confirm the demand-bound basis and allocations. Examine cooling separately if the decision requires it. |
| B | Not supported | Internal section after protection: −100 kW at 12:00–13:00; −150 at 13:00–14:00 UTC. | Confirm the internal section rating and allocation; agree any engineering alternative before reassessment. |
| C | Unknown | The protected grid-allocation record is missing; its remaining margin cannot be established. | Obtain the allocation owner, amount, completeness and non-overlap evidence, then confirm applicability. |
No combined MW total and no ranking in this example. Holding A's changed-record case, alternative and coupled extension are separate assessments, not replacements for its row here.
Why the service rating does not settle each holding's result
Holding B has a 6,500 kW service with 500 kW protected, but its internal section is limited to 4,200 kW with 200 kW protected. At 13:00–14:00 UTC, existing demand of 3,150 kW plus 1,000 kW added load exceeds the section's 4,000 kW remaining allowance by 150 kW. Its minimum grid-service margin is still +1,850 kW.
Holding C has a 5,500 kW service and a 6,000 kW section with 150 kW protected at the section. Positive physical margins do not establish how much grid service remains after commitments: that allocation is missing. It must not be assumed to be zero.
All values are assumed full-interval demand bounds. Applicable ratings and distinct commitments require responsible-engineer confirmation. These examples do not establish annual availability or total portfolio capacity.
EXAMPLES / DEPOT CHARGING STRATEGIES
Same trucks. Three charging strategies. Which one fits the depot's service?
Method: grid only (Headroom v2.1.0)
Simulated depot charging from real fleet operating schedules, with synthetic site limits. Not a customer result. All three strategies use the same simulated operating day.
A 50-truck warehouse-delivery depot needs its fleet charged for the next day's routes. On the same simulated operating day, charging every truck at 100 kW as soon as it comes off shift peaks at 3,100 kW, delaying that charging to the end of each off-shift period peaks at 4,000 kW, and spreading each truck's charging evenly over its time off shift peaks at 560.04 kW. Against the same synthetic service limit and protected depot load, the findings are Not supported, Not supported and Supported.
Delaying charging stacks every truck's session into the hours just before morning departures, so it produces the highest peak of the three.
Synthetic service limit: 2,600 kW. Existing depot demand: 200 kW, including auxiliaries. An additional 150 kW is protected for depot duties above that existing demand, leaving 2,250 kW for charging.
| Strategy | Peak 15-min average (kW) | Highest instant (kW) | Lowest spare capacity (kW) | When | Finding |
|---|---|---|---|---|---|
| Immediate (100 kW) | 2,993.56 | 3,100 | −850 | 17:15–17:45 | Not supported |
| Delayed (100 kW) | 3,488.33 | 4,000 | −1,750 | 07:15–07:45 | Not supported |
| Minimum power | 560.04 | 560.04 | +1,689.96 | Overnight, while all trucks charge | Supported |
Highest instant: the highest one-second demand in the interval, from the source model's simulation, rounded outward to 0.001 kW for assessment. Lowest spare capacity: the 2,250 kW charging allowance minus that demand. "Supported" applies under the stated synthetic site assumptions only. 15-minute averages are for display.
Why it matters: The charging strategy can matter as much as the number of trucks. A site that fails one plan may support another without new grid capacity.
Next action: Confirm the depot's service limit, the protected load and the fleet's actual schedules before choosing a strategy.
Same-day selection and assessment basis
Internal section limit: 3,100 kW, with 0 kW separately reserved at that section.
The minimum-power minimum margin occurs during 00:00–07:45, 20:45–22:30, 23:00–24:00 in source-model time.
The selected sample is day 49 of 50: the highest required fleet charging energy, chosen before calculating any strategy profile. Each strategy uses the same sampled vehicle schedules. The full model day is assessed in 96 contiguous 15-minute intervals. The date November 19, 2026, 00:00–24:00 UTC is a synthetic assessment anchor, not the date or timezone of a measured fleet day.
These are bounds derived from the source model's 1-second simulated output. The model's export convention repeats its first simulated value to complete a full day. Lower bounds, upper bounds, averages and energy accounting are retained in the download. The upper bounds determine the electrical checks; averages are not treated as bounds.
The service allowance was fixed before assessment from the midpoint of the smallest and largest strategy upper-bound peaks, rounded down to a 50 kW step. Existing load and protected demand do not overlap. Added charging is the other-load component; added IT and cooling electricity are each 0 kW. No embedded supply, storage or export is assumed. A Supported finding applies under these stated synthetic assumptions. It does not establish available power at an actual depot.
Does minimum-power charging still fit when the trucks use more energy?
Even at 2.8 kWh per mile, about 56% more energy than the 1.8 kWh-per-mile baseline, minimum-power charging peaks at 871.17 kW: under 40% of the 2,250 kW charging allowance. All three cases are Supported under the stated synthetic site assumptions.
Same 50 trucks, simulated operating day and vehicle schedules. All three efficiency cases retain the original synthetic limits: 2,600 kW service, 3,100 kW internal section, 200 kW existing load and 150 kW additional protection. The 2,250 kW charging allowance was not increased for this sensitivity.
Battery and operating limits: These results check power and daily energy only. The highest individual truck charging rate at 2.8 kWh per mile is 35.52 kW, below the 100 kW chargers. Battery sizes and starting charge weren't supplied, and one truck drives twice in the day, so a full charge before every departure isn't proven. Real battery, charger and route records would be needed before treating the fleet as ready for dispatch.
What this establishes: Electrical fit and daily energy balance for the supplied modeled schedules and synthetic site. It does not establish available power at a real depot, current utility capacity, or capacity available for another use.
Efficiency sensitivity and energy accounting
| Energy consumption (kWh/mile) | Required daily energy (kWh) | Peak 15-min average (kW) | Highest instant (kW) | Lowest spare capacity (kW) | Electrical finding |
|---|---|---|---|---|---|
| 1.5 kWh/mile | 7,126.7 | 466.7 | 466.7 | +1,783.3 | Supported |
| 1.8 kWh/mile (baseline) | 8,552.04 | 560.04 | 560.04 | +1,689.96 | Supported |
| 2.8 kWh/mile | 13,303.17 | 871.17 | 871.17 | +1,378.83 | Supported |
Definitions as in the charging-strategies table above.
The study's supplementary information uses 1.5, 1.8 and 2.8 kWh per mile as energy-consumption scenarios. Here, the new profiles at 1.5 and 2.8 were generated through the unchanged source model for the same previously selected operating day; the 1.8 baseline profile was retained. No day was reselected and no site limit was refitted. Added IT, added cooling and section protection remain 0 kW; charging remains the other-load component.
At 2.8 kWh per mile, required and raw simulated daily energy both round to 13,303.17 kWh. The source's export convention repeats its first simulated second, adding 0.24 kWh and producing 13,303.41 kWh in the exported day. This is an export boundary effect, not additional route energy. Charger conversion losses, hardware performance and operational availability require separate evidence.
The minimum protected-service margin occurs during 00:00–07:45, 20:45–22:30 and 23:00–24:00 in source-model time, using the same synthetic November 19, 2026 UTC anchor. The download retains all 96 intervals per case and exact calculation values. These are modeled scenarios, not measured bounds on real-world vehicle efficiency.
Charging profiles: generated with code and fleet operating schedules published by the National Laboratory of the Rockies (NLR), formerly the National Renewable Energy Laboratory (NREL), for Borlaug et al., Nature Energy (2021); code licensed BSD-3-Clause, data set licensed CC BY 4.0. Service limit, depot load and protected allocation: synthetic. No endorsement by NLR, the study's utility co-authors or the U.S. Department of Energy is implied.
Electrical support does not resolve a cooling shortfall.
Method: grid only with bounded cooling (Headroom v2.1.0)
Synthetic example. Not a customer result.
Combined finding: Not supported. The shared stage has a −220 kW (thermal) margin during October 26, 2026, 12:00–13:00 UTC. Electrical support remains positive.
Why it matters: the original electrical finding is not enough to support a power-and-cooling commitment. This extension uses the original demand records, not the higher-demand reassessment or lower-load alternative.
Next action: obtain the shared-stage rating at the actual conditions, shared-user allocations and reserve basis. Have the responsible engineer investigate the constraint before separately evaluating an alternative.
Decision: does the original Holding A proposal also fit the declared mixed air/liquid cooling path and shared heat-rejection stage?
| Domain | Basis | Margin | Finding |
|---|---|---|---|
| Electrical | 6,000 kW service − 400 kW protection − 5,020 kW demand | +580 kW (electrical) | Supported |
| Thermal | 4,800 kW shared rejection capacity − 5,020 kW heat demand | −220 kW (thermal) | Not supported |
| Combined | A known thermal failure remains despite electrical support. | Electrical and thermal margins are not added. | Not supported |
Thermal assumptions and full-window values
Assuming all IT electricity becomes heat inside this boundary, 70% of IT heat is captured by the liquid branch. Cooling electricity is already included in facility demand and is not counted twice. Cooling and other electrical heat are accounted for in the shared rejection demand. Air and liquid stages are not the limiting elements here.
| Hour UTC | Heat demand | Capacity | Margin |
|---|---|---|---|
| 09:00–10:00 | 4,000 | 6,200 | +2,200 |
| 10:00–11:00 | 4,350 | 6,000 | +1,650 |
| 11:00–12:00 | 4,800 | 5,900 | +1,100 |
| 12:00–13:00 | 5,020 | 4,800 | −220 |
| 13:00–14:00 | 4,700 | 5,100 | +400 |
| 14:00–15:00 | 4,150 | 6,100 | +1,950 |
The physical-capacity and protected-service checks identify the same 220 kW (thermal) shortfall, not two additive deficiencies. Capacities are supplied for each interval's conditions and apply to both baseline and proposal. Valid heat paths, flow/distribution and allocations are assumed. No transient response, redundancy standard, safe shorter duration or economical remedy is established.
Four findings, kept distinct.
- Supported
- The required evaluated checks support the supplied scenario within its stated conditions.
- Not supported
- A known constraint prevents support, even when other checks pass or evidence is missing.
- Unknown
- Required evidence prevents a conclusion, and no established failure determines the finding.
- Not evaluated
- The question or domain was not assessed.
Unknown does not mean zero physical capacity. Electrical, thermal and combined findings stay separate. These reviewed synthetic demonstrations do not establish customer validation, production deployment, engineering approval or permission to operate.
The downloads contain selected inputs and findings, not complete replay packages. A source hash identifies retained file bytes; it does not reproduce a calculation without those records.
One site. One question. An agreed period.
First Site Evaluation
Start with a fit discussion by email. The paid assessment covers one site and one decision, with scope, quote, authorization and data handling agreed before records are shared.
Standard assessments: a written finding within five business days after scope is agreed and the required records are confirmed. Broader assessments, including coupled power-and-cooling work, follow the schedule agreed in the written quote.
Review the records checklist and who develops Headroom. No sensitive records are needed for the initial inquiry.
Read-only, export-based and analyst-assisted. Findings apply to a supplied proposal, defined period and supported method; they are not operating approval or guaranteed capacity. Public capacity examples are synthetic. Customer-site validation and qualified external engineering review remain outstanding. Method boundaries and verification
